Sports arena Lora, Croatia

Sports arena Lora, Split, Croatia - The PERI solution served as both shoring and an assembly platform on which the enormous steel trusses of the roof construction were set down, assembled and moved into position.
Sports arena Lora, Split, Croatia - With point load concentrations, several standards could be bundled together using short 25 cm ledgers of the PERI UP modular scaffolding system.
Sports arena Lora, Split, Croatia - The 7 m wide and 58 m long working platform carried by horizontally-positioned PERI brace frames.
Sports arena Lora, Split, Croatia - For the final assembly of the over 80 m long roof construction, the PERI UP assembly platform was extended to a width of 14 m in the internal area.
Sports arena Lora, Split, Croatia - The multi-functional arena in Split, with seating for 12,500 spectators, was finished in time for the 2009 handball world championships which took place in Croatia.

Données des projets

Localisation: Split, Croatie

Multi-purpose hall with octagonal layout, 120 m x 80 m, and 12,500 seats

Finished: 2009 for the handball world championship in Croatia

Exigences

  • erecting scaffolding for 8 steel lattice girders
  • 180 tons of load per pair of trusses

Client

Dinarik d.o.o., Donji Prolozac

Avantages pour le client

  • cost-effective roof assembly
  • safe and fast erecting work
  • economic solution with system parts
 Oliver Pezer, Work preparation and logistics, Statement Sportarena Lora
Oliver Pezer
Work preparation and logistics

We chose PERI because of the professional formwork planning and support. All technical requirements were met in a cost-effective way with the PERI systems.

Solution PERI

  • PERI UP as shoring and erecting platform
  • brace frames used in suspended position as 7 m protruding support structure